PK0-005 · Question #492

A project team in a projectized organization has been struggling due to some members performing duties that are assigned to others. Which of the following steps should the project manager take next…

The correct answer is D. Review the RACI matrix with the team. Reviewing the RACI matrix clarifies roles and responsibilities, helping eliminate confusion about task ownership. This directly addresses the issue of team members performing duties not assigned to them.

Tools and documentation

Question

A project team in a projectized organization has been struggling due to some members performing duties that are assigned to others. Which of the following steps should the project manager take next in solving this issue?

Options

  • AEscalate the issue to the management team.
  • BDiscuss the project charter during a team meeting.
  • CAsk the team to be open for collaboration.
  • DReview the RACI matrix with the team.

How the community answered

(30 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    7% (2)
  • D
    80% (24)

Explanation

Reviewing the RACI matrix clarifies roles and responsibilities, helping eliminate confusion about task ownership. This directly addresses the issue of team members performing duties not assigned to them.

Topics

#Project Team Management#Roles and Responsibilities#RACI Matrix#Conflict Resolution