During a meeting, a project manager notices that a key team member has issues with delivering content to stakeholders. Which of the following should the project manager do next?

The correct answer is C. Encourage the team member to attend training classes. Encouraging the team member to attend training classes addresses the root cause - improving communication or presentation skills - rather than bypassing or replacing them. This supports professional development and long-term performance improvement.

Project Management Concepts

Question

During a meeting, a project manager notices that a key team member has issues with delivering content to stakeholders. Which of the following should the project manager do next?

Options

  • ARequest a replacement team member.
  • BPresent on behalf of the team member.
  • CEncourage the team member to attend training classes.
  • DAsk other team members to present.

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    76% (16)
  • D
    14% (3)

Explanation

Encouraging the team member to attend training classes addresses the root cause - improving communication or presentation skills - rather than bypassing or replacing them. This supports professional development and long-term performance improvement.

Topics

#Team development#Performance management#Skill gap resolution#Stakeholder communication