PK0-005 · Question #488
PK0-005 Question #488: Real Exam Question with Answer & Explanation
The correct answer is C: Encourage the team member to attend training classes.. Encouraging the team member to attend training classes addresses the root cause - improving communication or presentation skills - rather than bypassing or replacing them. This supports professional development and long-term performance improvement.
Question
During a meeting, a project manager notices that a key team member has issues with delivering content to stakeholders. Which of the following should the project manager do next?
Options
- ARequest a replacement team member.
- BPresent on behalf of the team member.
- CEncourage the team member to attend training classes.
- DAsk other team members to present.
Explanation
Encouraging the team member to attend training classes addresses the root cause - improving communication or presentation skills - rather than bypassing or replacing them. This supports professional development and long-term performance improvement.