PK0-005 · Question #487
PK0-005 Question #487: Real Exam Question with Answer & Explanation
The correct answer is D: Assessing stakeholders. Assessing stakeholders is a key activity during the initiation phase to identify who is impacted by the project and understand their interests and influence. This informs planning and engagement strategies used throughout the project.
Project Life Cycle Phases
Question
A project manager needs to prepare for the project kickoff during the initiation phase. Which of the following activities should be conducted?
Options
- AEstablishing accepted communication channels
- BDeveloping the records management plan
- CReviewing existing artifacts
- DAssessing stakeholders
Explanation
Assessing stakeholders is a key activity during the initiation phase to identify who is impacted by the project and understand their interests and influence. This informs planning and engagement strategies used throughout the project.
Topics
#Project Initiation#Stakeholder Assessment#Project Kickoff Preparation#Project Life Cycle