nerdexam
CompTIACompTIA

PK0-005 · Question #487

PK0-005 Question #487: Real Exam Question with Answer & Explanation

The correct answer is D: Assessing stakeholders. Assessing stakeholders is a key activity during the initiation phase to identify who is impacted by the project and understand their interests and influence. This informs planning and engagement strategies used throughout the project.

Project Life Cycle Phases

Question

A project manager needs to prepare for the project kickoff during the initiation phase. Which of the following activities should be conducted?

Options

  • AEstablishing accepted communication channels
  • BDeveloping the records management plan
  • CReviewing existing artifacts
  • DAssessing stakeholders

Explanation

Assessing stakeholders is a key activity during the initiation phase to identify who is impacted by the project and understand their interests and influence. This informs planning and engagement strategies used throughout the project.

Topics

#Project Initiation#Stakeholder Assessment#Project Kickoff Preparation#Project Life Cycle

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions