The correct answer is B: Key performance indicators. KPIs (Key Performance Indicators) are measurable values tied to project goals. If KPIs are being met, the PM can confirm that the project outcomes align with objectives. Audit reports verify compliance, while lessons learned capture knowledge at project closure.
Project Management Concepts
Question
Which of the following would help a project manager identify that project goals have been reached?
Options
- AAudit report
- BKey performance indicators
- CBacklog
- DLessons learned
Explanation
KPIs (Key Performance Indicators) are measurable values tied to project goals. If KPIs are being met, the PM can confirm that the project outcomes align with objectives. Audit reports verify compliance, while lessons learned capture knowledge at project closure.
Topics
#Key Performance Indicators (KPIs)#Project Monitoring#Performance Measurement#Project Goals
Community Discussion
No community discussion yet for this question.