The correct answer is B: Follow up on the payment request with the payable clerk.. In a functional organizational structure, the project manager has limited authority over budgets and financial decisions. Since the mobilization fee payment is an operational finance issue, the project manager should follow up with the payable clerk, who handles payment processin
Question
In a functional organizational structure, a project manager is trying to avoid a project roadblock due to a mobilization fee that has not been paid to a contractor. Which of the following should the project manager do?
Options
- AAuthorize payment from the contingency budget.
- BFollow up on the payment request with the payable clerk.
- CNegotiate with the contractor to be paid later in the project.
- DEscalate the issue to the financial controller.
Explanation
In a functional organizational structure, the project manager has limited authority over budgets and financial decisions. Since the mobilization fee payment is an operational finance issue, the project manager should follow up with the payable clerk, who handles payment processing. This ensures the payment request is progressing and helps avoid unnecessary escalations or delays.