PK0-005 · Question #413
A project manager is working with a new team to review a requirement for a new project. The project manager wants to create artifacts that include roles and responsibilities. Which of the following…
The correct answer is A. RACI chart. A RACI chart (Responsible, Accountable, Consulted, Informed) is specifically designed to document roles and responsibilities for tasks, decisions, and deliverables on a project. It clearly maps who does the work, who owns the outcome, who must be consulted, and who must be kept…
Question
A project manager is working with a new team to review a requirement for a new project. The project manager wants to create artifacts that include roles and responsibilities. Which of the following artifact types best matches these requirements?
Options
- ARACI chart
- BGantt chart
- CBurndown chart
- DOrganizational chart
How the community answered
(37 responses)- A92% (34)
- B5% (2)
- D3% (1)
Explanation
A RACI chart (Responsible, Accountable, Consulted, Informed) is specifically designed to document roles and responsibilities for tasks, decisions, and deliverables on a project. It clearly maps who does the work, who owns the outcome, who must be consulted, and who must be kept informed. A Gantt chart shows the project schedule and task timelines. A burndown chart tracks remaining work in agile sprints. An organizational chart shows reporting hierarchy but does not map responsibilities to specific project activities.