The correct answer is A: Baseline. The baseline should be developed to formalize the agreement on the tasks, durations, predecessors, and resources. The project baseline includes the approved version of the project schedule, cost, and scope, which is used as a reference to track the project's performance. It serve
Question
During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?
Options
- ABaseline
- BRBS
- CWBS
- DMilestones
Explanation
The baseline should be developed to formalize the agreement on the tasks, durations, predecessors, and resources. The project baseline includes the approved version of the project schedule, cost, and scope, which is used as a reference to track the project's performance. It serves as a formal and agreed-upon plan that is used to measure and compare the actual progress throughout the project's lifecycle.
Topics
Community Discussion
No community discussion yet for this question.