nerdexam
CompTIACompTIA

PK0-005 · Question #392

PK0-005 Question #392: Real Exam Question with Answer & Explanation

The correct answer is A: Review the project risk register.. The first step for the project manager should be to review the project risk register. The risk register is where potential risks to the project, including potential blockers, are documented. By reviewing the risk register, the project manager can determine if these potential area

Tools and documentation

Question

A new project manager was assigned to a project during the execution phase. The project manager discovers a lot of potential areas that may prevent the project from completing deliverables. Which of the following should the project manager do first?

Options

  • AReview the project risk register.
  • BUpdate the defect tracker.
  • CMeet with stakeholders to discuss concerns.
  • DAdd the potential blockers to the issues list.

Explanation

The first step for the project manager should be to review the project risk register. The risk register is where potential risks to the project, including potential blockers, are documented. By reviewing the risk register, the project manager can determine if these potential areas have already been identified, assess their potential impact, and decide on the appropriate actions to mitigate or manage them moving forward.

Topics

#Project Risk Management#Risk Register#Project Execution Phase#Project Management Tools

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions