PK0-005 · Question #392
PK0-005 Question #392: Real Exam Question with Answer & Explanation
The correct answer is A: Review the project risk register.. The first step for the project manager should be to review the project risk register. The risk register is where potential risks to the project, including potential blockers, are documented. By reviewing the risk register, the project manager can determine if these potential area
Question
A new project manager was assigned to a project during the execution phase. The project manager discovers a lot of potential areas that may prevent the project from completing deliverables. Which of the following should the project manager do first?
Options
- AReview the project risk register.
- BUpdate the defect tracker.
- CMeet with stakeholders to discuss concerns.
- DAdd the potential blockers to the issues list.
Explanation
The first step for the project manager should be to review the project risk register. The risk register is where potential risks to the project, including potential blockers, are documented. By reviewing the risk register, the project manager can determine if these potential areas have already been identified, assess their potential impact, and decide on the appropriate actions to mitigate or manage them moving forward.