PK0-005 · Question #391
PK0-005 Question #391: Real Exam Question with Answer & Explanation
The correct answer is C: Risk, issue. Risk: The project manager identifies and captures the potential change (e.g., resources being pulled to a higher priority project) as a risk based on indicators. Issue: The risk then materializes into an actual issue when the resources are actually pulled off the project, impacti
Question
A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?
Options
- AIssue, issue
- BIssue, risk
- CRisk, issue
- DRisk, risk
Explanation
Risk: The project manager identifies and captures the potential change (e.g., resources being pulled to a higher priority project) as a risk based on indicators. Issue: The risk then materializes into an actual issue when the resources are actually pulled off the project, impacting the project's
Topics
Community Discussion
No community discussion yet for this question.