nerdexam
CompTIACompTIA

PK0-005 · Question #391

PK0-005 Question #391: Real Exam Question with Answer & Explanation

The correct answer is C: Risk, issue. Risk: The project manager identifies and captures the potential change (e.g., resources being pulled to a higher priority project) as a risk based on indicators. Issue: The risk then materializes into an actual issue when the resources are actually pulled off the project, impacti

Project Management Concepts

Question

A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?

Options

  • AIssue, issue
  • BIssue, risk
  • CRisk, issue
  • DRisk, risk

Explanation

Risk: The project manager identifies and captures the potential change (e.g., resources being pulled to a higher priority project) as a risk based on indicators. Issue: The risk then materializes into an actual issue when the resources are actually pulled off the project, impacting the project's

Topics

#Risk Management#Issue Management#Project Planning

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions