PK0-005 · Question #391

A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information bas

The correct answer is C. Risk, issue. Risk: The project manager identifies and captures the potential change (e.g., resources being pulled to a higher priority project) as a risk based on indicators. Issue: The risk then materializes into an actual issue when the resources are actually pulled off the project, impacti

Project Management Concepts

Question

A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?

Options

  • AIssue, issue
  • BIssue, risk
  • CRisk, issue
  • DRisk, risk

How the community answered

(54 responses)
  • A
    4% (2)
  • B
    7% (4)
  • C
    74% (40)
  • D
    15% (8)

Explanation

Risk: The project manager identifies and captures the potential change (e.g., resources being pulled to a higher priority project) as a risk based on indicators. Issue: The risk then materializes into an actual issue when the resources are actually pulled off the project, impacting the project's

Topics

#Risk Management#Issue Management#Project Planning