A project team has implemented a new system and needs to ensure it is usable. Which of the following should be performed first?

The correct answer is A. Provide end-user training. Providing end-user training is the first step to ensure that the system is usable. It is essential to equip users with the necessary knowledge and skills to effectively use the new system. Without proper training, the users may face difficulties in adopting the system, which…

Project Life Cycle Phases

Question

A project team has implemented a new system and needs to ensure it is usable. Which of the following should be performed first?

Options

  • AProvide end-user training.
  • BDecommission old systems.
  • CRelease external consultants.
  • DMonitor performance.

How the community answered

(26 responses)
  • A
    85% (22)
  • B
    12% (3)
  • D
    4% (1)

Explanation

Providing end-user training is the first step to ensure that the system is usable. It is essential to equip users with the necessary knowledge and skills to effectively use the new system. Without proper training, the users may face difficulties in adopting the system, which could impact its overall effectiveness and usability.