nerdexam
CompTIACompTIA

PK0-005 · Question #299

PK0-005 Question #299: Real Exam Question with Answer & Explanation

The correct answer is A: Ask a developer to create a change request.. {"question_number": 5, "explanation": "The PM should ask the developer to submit a formal change request. Although the performance fix has merit, modifying code outside the defined project scope requires going through the change control process - this ensures the change is review

Project Management Concepts

Question

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

Options

  • AAsk a developer to create a change request.
  • BDo nothing because recommendation is scope creep.
  • CAsk a developer to implement the recommendation.
  • DCommunicate the change status.

Explanation

{"question_number": 5, "explanation": "The PM should ask the developer to submit a formal change request. Although the performance fix has merit, modifying code outside the defined project scope requires going through the change control process - this ensures the change is reviewed, approved, budgeted, and documented. Simply implementing it would be unauthorized scope change. Doing nothing ignores a legitimate performance concern. Communicating change status is premature before the change has been formally submitted and evaluated. The change request process protects both the project and the developer.", "generated_by": "claude-sonnet", "llm_judge_score": 4}

Topics

#Change Management#Scope Management#Project Manager Role#Performance Issues

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions