PK0-005 · Question #268
Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?
The correct answer is A. Reviewing project blockers. According to Four agile ceremonies, demystified, one of the Scrum ceremonies is the daily stand- up, which is a short meeting to discuss progress and identify blockers. Blockers are any issues or impediments that prevent the team from completing their tasks or achieving their…
Question
Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?
Options
- AReviewing project blockers
- BDefining roles and responsibilities
- CEstablishing a project schedule
- DDetermining a project budget
How the community answered
(38 responses)- A92% (35)
- B5% (2)
- D3% (1)
Explanation
According to Four agile ceremonies, demystified, one of the Scrum ceremonies is the daily stand- up, which is a short meeting to discuss progress and identify blockers. Blockers are any issues or impediments that prevent the team from completing their tasks or achieving their goals. Reviewing project blockers during the daily stand-up helps the team to resolve them quickly, collaborate effectively, and stay on track. The other options are not likely to take place during a Scrum ceremony, as they are either part of the initial project planning or outside the scope of
Topics