PK0-005 · Question #267
Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?
The correct answer is A. Maintenance window. A maintenance window is a predefined period of time during which planned changes or updates can be performed on a system or network with minimal impact on the users or business operations. A project manager should consider the maintenance window next when deploying a new…
Question
Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?
Options
- AMaintenance window
- BRisk assessment
- COperational security
- DValidation check
How the community answered
(50 responses)- A82% (41)
- B4% (2)
- C12% (6)
- D2% (1)
Explanation
A maintenance window is a predefined period of time during which planned changes or updates can be performed on a system or network with minimal impact on the users or business operations. A project manager should consider the maintenance window next when deploying a new networking device into an existing production environment, as it will help to reduce the risk of downtime, disruption, or errors. A maintenance window should be scheduled in advance, communicated to the stakeholders, and aligned with the change management plan.