CompTIACompTIA
PK0-005 · Question #264
PK0-005 Question #264: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-005 to reveal the answer and full explanation for question #264. The question stem and answer options stay visible for context.
Project Management Concepts
Question
In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?
Options
- AAdd a new risk.
- BPerform an impact analysis.
- CEscalate to the sponsor.
- DRaise a change request.
Unlock PK0-005 to see the answer
You've previewed enough free PK0-005 questions. Unlock PK0-005 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Schedule Management#Resource Management#Impact Analysis#Project Change Control