PK0-005 · Question #245
PK0-005 Question #245: Real Exam Question with Answer & Explanation
The correct answer is B: Complete the project sign-off.. The project sign-off is the formal acceptance of the project deliverables by the client, stakeholder, or customer. It also marks the closure of the project and the release of the final payment. If the project sign-off is not completed, the project may still incur costs and liabil
Question
The quarterly financial report displays losses from a project even though the project was completed successfully several weeks ago. Which of the following actions should the project manager perform next?
Options
- ARemove access.
- BComplete the project sign-off.
- CRelease the resources.
- DOutline the lessons learned.
Explanation
The project sign-off is the formal acceptance of the project deliverables by the client, stakeholder, or customer. It also marks the closure of the project and the release of the final payment. If the project sign-off is not completed, the project may still incur costs and liabilities, which can explain the losses in the financial report. Therefore, the project manager should complete the project sign-off as soon as possible to avoid further losses.
Topics
Community Discussion
No community discussion yet for this question.