PK0-005 · Question #222
A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?
The correct answer is B. Closing. Identifying the go-live date, planning operational training, and defining handoff procedures are all activities associated with the Closing phase. These activities focus on transitioning the deliverable to the operations team or customer, which is a hallmark of project closure…
Question
A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?
Options
- AInitiation
- BClosing
- CExecution
- DPlanning
How the community answered
(41 responses)- A15% (6)
- B71% (29)
- C10% (4)
- D5% (2)
Explanation
Identifying the go-live date, planning operational training, and defining handoff procedures are all activities associated with the Closing phase. These activities focus on transitioning the deliverable to the operations team or customer, which is a hallmark of project closure. Initiation (A) involves high-level scope and authorization. Planning (D) covers creating schedules, budgets, and plans. Execution (C) is where the actual work is performed. Establishing handoff procedures and operational readiness is definitively a closing activity.