During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?

The correct answer is A. Obtain details from the owner of the project. Before taking any corrective action - updating the critical path, applying reserves, or re-estimating - the program manager must first gather the facts. Obtaining details from the project owner clarifies the scope of the delay, its root cause, the current forecast, and any…

Project Management Concepts

Question

During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?

Options

  • AObtain details from the owner of the project.
  • BUpdate the critical path for the project.
  • CApply contingency reserves.
  • DReestimate epic user stories.

How the community answered

(35 responses)
  • A
    89% (31)
  • B
    6% (2)
  • C
    3% (1)
  • D
    3% (1)

Explanation

Before taking any corrective action - updating the critical path, applying reserves, or re-estimating - the program manager must first gather the facts. Obtaining details from the project owner clarifies the scope of the delay, its root cause, the current forecast, and any mitigation already underway. Acting without this information risks incorrect responses. This reflects the principle of 'gather information before acting' in issue management.

Topics

#Program Management#Issue Management#Dependency Management#Communication

Community Discussion

No community discussion yet for this question.