PK0-005 · Question #221
PK0-005 Question #221: Real Exam Question with Answer & Explanation
The correct answer is A: Obtain details from the owner of the project.. The program manager should first obtain details from the owner of the project that is causing the delay, such as the root cause, the impact, the mitigation plan, and the revised timeline. This will help the program manager to assess the situation, communicate with the stakeholder
Question
During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?
Options
- AObtain details from the owner of the project.
- BUpdate the critical path for the project.
- CApply contingency reserves.
- DReestimate epic user stories.
Explanation
The program manager should first obtain details from the owner of the project that is causing the delay, such as the root cause, the impact, the mitigation plan, and the revised timeline. This will help the program manager to assess the situation, communicate with the stakeholders, and adjust the program schedule accordingly. Updating the critical path, applying contingency reserves, and reestimating epic user stories are possible actions that the program manager may take after obtaining the details, depending on the severity and duration of the delay. However, they are not the immediate next steps, as they require more information and analysis.