PK0-005 · Question #219
Which of the following activities are performed during the closing phase? (Select three).
The correct answer is B. Recognizing project team efforts and rewarding team members D. Revoking resource credentials from the system F. Informing the functional manager about the release of resources. Closing phase activities involve wrapping up the project administratively and releasing resources. Recognizing and rewarding team members (B) is a formal closure activity. Revoking resource credentials (D) is part of administratively closing out system access. Informing…
Question
Which of the following activities are performed during the closing phase? (Select three).
Options
- ARequesting project charter sign-off
- BRecognizing project team efforts and rewarding team members
- CWorking with the financial team to obtain return of investment
- DRevoking resource credentials from the system
- EUpdating the risk register with new findings
- FInforming the functional manager about the release of resources
- GMonitoring project team performance
How the community answered
(29 responses)- A3% (1)
- B90% (26)
- E7% (2)
Explanation
Closing phase activities involve wrapping up the project administratively and releasing resources. Recognizing and rewarding team members (B) is a formal closure activity. Revoking resource credentials (D) is part of administratively closing out system access. Informing functional managers of resource release (F) returns people to their home departments. Requesting charter sign-off (A) is Initiation; updating the risk register (E) and monitoring performance (G) are Execution/Monitoring activities; ROI work (C) is typically done during business case development, not project closure.
Topics