nerdexam
CompTIA

PK0-005 · Question #213

A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have…

The correct answer is A. Removing access. Removing access means revoking the contractor's permissions to access the project data, systems, and devices after the project is closed. This is a crucial security measure to prevent unauthorized access, misuse, or theft of sensitive data by external parties. Closing…

Project Life Cycle Phases

Question

A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?

Options

  • ARemoving access
  • BClosing contracts
  • CProject sign-off
  • DProject evaluation

How the community answered

(42 responses)
  • A
    74% (31)
  • B
    14% (6)
  • C
    2% (1)
  • D
    10% (4)

Explanation

Removing access means revoking the contractor's permissions to access the project data, systems, and devices after the project is closed. This is a crucial security measure to prevent unauthorized access, misuse, or theft of sensitive data by external parties. Closing contracts, project sign-off, and project evaluation are important steps in the project closure process, but they do not necessarily prevent data theft by themselves. They may involve formal agreements, documentation, and feedback, but they do not address the technical aspects of data security.

Topics

#Project Closure#Access Management#Contractor Management#Data Security

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice