PK0-005 · Question #204

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

The correct answer is E. Validating the deliverables F. Reconciling the project budget. During the project closure phase in the waterfall methodology, it is crucial to validate the deliverables to ensure that all project requirements have been met and the project outputs are complete and satisfactory. Additionally, reconciling the project budget is performed to…

Project Life Cycle Phases

Question

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

Options

  • ACreating a backlog
  • BManaging the quality of deliverables
  • CUpdating the issue log
  • DPerforming a risk assessment
  • EValidating the deliverables
  • FReconciling the project budget

How the community answered

(23 responses)
  • C
    9% (2)
  • D
    4% (1)
  • E
    87% (20)

Explanation

During the project closure phase in the waterfall methodology, it is crucial to validate the deliverables to ensure that all project requirements have been met and the project outputs are complete and satisfactory. Additionally, reconciling the project budget is performed to ensure all financial records are accurate and reflect the actual project costs, which is essential for the formal closing of the project.

Topics

#Project Closure#Project Life Cycle#Waterfall Methodology#Deliverable Validation