A project coordinator has started a new project and is reviewing the following characteristics provided by the customer: - Two developers - High uncertainty about existing systems - Risk of frequent…
The correct answer is B. Scrum. This answer is based on the best practice of choosing a project management methodology that suits the project characteristics and environment. Scrum is an agile framework that is designed to handle complex and uncertain projects with frequent changes and tight deadlines. Scrum…
Question
A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:
- Two developers
- High uncertainty about existing systems
- Risk of frequent requirement changes
- Tight deadlines
Which of the following project methodologies would be best to use in this situation?
Options
- APRINCE2
- BScrum
- CSAFe
- DXP
How the community answered
(18 responses)- A6% (1)
- B78% (14)
- C11% (2)
- D6% (1)
Explanation
This answer is based on the best practice of choosing a project management methodology that suits the project characteristics and environment. Scrum is an agile framework that is designed to handle complex and uncertain projects with frequent changes and tight deadlines. Scrum involves a small, cross-functional team that works in short iterations called sprints, delivering incremental and potentially shippable products at the end of each sprint. Scrum also allows for continuous feedback and improvement through daily stand-up meetings, sprint reviews, and retrospectives. Scrum is suitable for this project because it can accommodate the high uncertainty, the risk of requirement changes, and the tight deadlines, while also enabling the two developers to collaborate effectively and deliver value to the customer.