PK0-005 · Question #173

PK0-005 Question #173: Real Exam Question with Answer & Explanation

The correct answer is C: Burndown chart. A burndown chart is a visual representation of the remaining work versus the time required to complete it. It is commonly used by agile teams to track the progress of each iteration or sprint and to forecast the project completion date. A burndown chart shows the ideal work remai

Tools and documentation

Question

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

Options

  • APareto chart
  • BMilestone chart
  • CBurndown chart
  • DGantt chart

Explanation

A burndown chart is a visual representation of the remaining work versus the time required to complete it. It is commonly used by agile teams to track the progress of each iteration or sprint and to forecast the project completion date. A burndown chart shows the ideal work remaining line and the actual work remaining line, which can help the team identify any deviations or impediments and adjust accordingly. A burndown chart is different from a Pareto chart, which shows the frequency of different causes of problems; a milestone chart, which shows the key events and deliverables of a project; and a Gantt chart, which shows the dependencies and durations of tasks in a project.

Topics

#Agile project management#Burndown charts#Project tracking#Project forecasting