PK0-005 · Question #172
Which of the following can a project manager infer from the following velocity chart?
The correct answer is C. The project is behind schedule. The velocity chart typically shows the amount of work completed over time. If the "Actual Effort" line is below the "Planned Timeline," it indicates that the project is not progressing as fast as planned, hence it is behind schedule. This is inferred by comparing the actual…
Question
Which of the following can a project manager infer from the following velocity chart?
Exhibit
Options
- AThe project is on schedule.
- BThe project Is ahead of schedule.
- CThe project is behind schedule.
- DThe project is at risk.
How the community answered
(36 responses)- A14% (5)
- B3% (1)
- C78% (28)
- D6% (2)
Explanation
The velocity chart typically shows the amount of work completed over time. If the "Actual Effort" line is below the "Planned Timeline," it indicates that the project is not progressing as fast as planned, hence it is behind schedule. This is inferred by comparing the actual work completed against what was scheduled.
Topics