PK0-005 · Question #172

Which of the following can a project manager infer from the following velocity chart?

The correct answer is C. The project is behind schedule. The velocity chart typically shows the amount of work completed over time. If the "Actual Effort" line is below the "Planned Timeline," it indicates that the project is not progressing as fast as planned, hence it is behind schedule. This is inferred by comparing the actual…

Project Management Concepts

Question

Which of the following can a project manager infer from the following velocity chart?

Exhibit

PK0-005 question #172 exhibit

Options

  • AThe project is on schedule.
  • BThe project Is ahead of schedule.
  • CThe project is behind schedule.
  • DThe project is at risk.

How the community answered

(36 responses)
  • A
    14% (5)
  • B
    3% (1)
  • C
    78% (28)
  • D
    6% (2)

Explanation

The velocity chart typically shows the amount of work completed over time. If the "Actual Effort" line is below the "Planned Timeline," it indicates that the project is not progressing as fast as planned, hence it is behind schedule. This is inferred by comparing the actual work completed against what was scheduled.

Topics

#Velocity charts#Project tracking#Agile metrics#Project status