PK0-005 · Question #144

PK0-005 Question #144: Real Exam Question with Answer & Explanation

Sign in or unlock PK0-005 to reveal the answer and full explanation for question #144. The question stem and answer options stay visible for context.

Project Management Concepts

Question

During the course of a project, an unexpected event occurs that could ultimately benefit the company. Which of the following is the company employing if the company decides to take advantage of this opportunity?

Options

  • AExploit
  • BEnhance
  • CAccept
  • DMitigate

Unlock PK0-005 to see the answer