PK0-005 · Question #143
During the planning phase, a project manager held a meeting to discuss meeting days, meeting times, meeting frequency, and tools to use. Which of the following will the project manager use to…
The correct answer is A. Project communication plan. Details about how, when, and with what tools project information will be shared are formally documented in the communication plan.
Question
During the planning phase, a project manager held a meeting to discuss meeting days, meeting times, meeting frequency, and tools to use. Which of the following will the project manager use to document this data?
Options
- AProject communication plan
- BProject charter
- CProject management plan
- DProject plan
How the community answered
(33 responses)- A94% (31)
- B3% (1)
- D3% (1)
Why each option
Details about how, when, and with what tools project information will be shared are formally documented in the communication plan.
The project communication plan outlines how project information will be exchanged, including details like meeting schedules (days, times, frequency), communication methods, and the tools to be used (e.g., email, collaboration platforms). It ensures all stakeholders are informed effectively and consistently throughout the project lifecycle.
The project charter formally authorizes the project and provides high-level objectives, but it does not detail communication logistics.
The project management plan is a comprehensive document that integrates all subsidiary plans, including the communication plan, but the specific details discussed are documented within the communication plan itself. 'Project management plan' is too broad for these specific details.
'Project plan' is a general term often used interchangeably with the project management plan, and like C, is too broad for this specific documentation.
Concept tested: Project communication planning