PK0-005 · Question #121
PK0-005 Question #121: Real Exam Question with Answer & Explanation
The correct answer is D: Communicate the change deployment.. After an approved change request leads to an updated project plan, the project manager's next step in the change control process is to communicate the change and its deployment details. This ensures all stakeholders are informed about the new plan and revised dates.
Question
As a result of an approved change request, the project manager updates the project plan to reflect the new feature addition and the revised production release date. Which of the following change control processes should the project manager do NEXT?
Options
- AValidate the change implementation.
- BImplement the change.
- CConduct an impact assessment.
- DCommunicate the change deployment.
Explanation
After an approved change request leads to an updated project plan, the project manager's next step in the change control process is to communicate the change and its deployment details. This ensures all stakeholders are informed about the new plan and revised dates.
Common mistakes.
- A. Validating change implementation occurs after the change has been implemented, not immediately after updating the plan.
- B. Implementing the change (executing the work) comes after communication and before validation.
- C. Conducting an impact assessment happens before a change request is approved, as it's part of the evaluation process to decide whether to approve the change.
Concept tested. Change control communication
Topics
Community Discussion
No community discussion yet for this question.