PK0-005 · Question #100
PK0-005 Question #100: Real Exam Question with Answer & Explanation
The correct answer is C: Coordinate a phase-gate review.. To assess if a completed project segment meets quality standards and if resources are adequate before proceeding, the project manager should coordinate a phase-gate review.
Question
A segment of a project has ended. Before moving on to the next segment, the project manager wants to assess if the work produced in the previous segment meets a high enough standard and if adequate resources are available to continue the project. Which of the following should the project manager do?
Options
- AReview the progress reports.
- BPerform a gap analysis.
- CCoordinate a phase-gate review.
- DSet up touch points with the team.
Explanation
To assess if a completed project segment meets quality standards and if resources are adequate before proceeding, the project manager should coordinate a phase-gate review.
Common mistakes.
- A. Reviewing progress reports provides updates but is less formal and comprehensive than a phase-gate review for making go/no-go decisions between project segments.
- B. Performing a gap analysis identifies differences between current and desired states, which is part of planning or problem-solving, but not the primary mechanism for formal phase transition approval.
- D. Setting up touch points with the team is for ongoing communication and minor check-ins, not a formal assessment and decision point for moving between major project segments.
Concept tested. Project lifecycle management and phase transitions
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/project-management-process-groups