A new project has started, and the project schedule is being built. After the WBS is complete, scheduling of the activities begins. Which of the following is the most likely NEXT step?

The correct answer is A. Sequence the activities. After the WBS is complete and activities are identified, the next step in schedule development is to sequence those activities by establishing their logical dependencies.

Project management concepts

Question

A new project has started, and the project schedule is being built. After the WBS is complete, scheduling of the activities begins. Which of the following is the most likely NEXT step?

Options

  • ASequence the activities.
  • BAllocate the resources.
  • CSet the baseline.
  • DDetermine the tasks.

How the community answered

(43 responses)
  • A
    91% (39)
  • B
    2% (1)
  • C
    2% (1)
  • D
    5% (2)

Why each option

After the WBS is complete and activities are identified, the next step in schedule development is to sequence those activities by establishing their logical dependencies.

ASequence the activities.Correct

Sequencing activities is the process of identifying and documenting the logical relationships among scheduled activities. After the WBS has decomposed deliverables into work packages and activities are defined, sequencing establishes predecessor-successor relationships and produces the project schedule network diagram, which is required before duration estimating or scheduling can proceed.

BAllocate the resources.

Resource allocation occurs later in schedule development, after activities have been defined and sequenced, because you must know the activity order and duration estimates before assigning resources effectively.

CSet the baseline.

Setting the schedule baseline is one of the final steps in planning, done only after the full schedule is developed, compressed, and approved - not at the beginning of scheduling.

DDetermine the tasks.

Determining tasks (Define Activities) is the step that precedes sequencing; since the question states the WBS is complete and scheduling has begun, activity definition is already done.

Concept tested: Project schedule development process order

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#activity sequencing#WBS#project scheduling#schedule development