PK0-004 · Question #923
A project manager is overseeing a project to launch a new satellite. While the satellite is being developed internally, a required piece to launch the system is provided by an external partner…
The correct answer is D. Mitigate the risk by requiring quality checkpoints. When a critical external component has a high failure rate, mitigation through quality checkpoints directly reduces the probability of failure rather than simply absorbing or shifting the consequence.
Question
A project manager is overseeing a project to launch a new satellite. While the satellite is being developed internally, a required piece to launch the system is provided by an external partner, which has experienced a high failure rate. Which of the following risk strategies should the project manager apply?
Options
- ATransfer the risk with an insurance plan to cover potential failures.
- BAvoid the risk by building the launch system internally.
- CAccept the risk as normal for this type of project.
- DMitigate the risk by requiring quality checkpoints.
How the community answered
(30 responses)- A7% (2)
- B7% (2)
- C3% (1)
- D83% (25)
Why each option
When a critical external component has a high failure rate, mitigation through quality checkpoints directly reduces the probability of failure rather than simply absorbing or shifting the consequence.
Insurance transfers only the financial consequences of failure to a third party but does nothing to reduce the high failure rate itself, leaving the project exposed to schedule and technical impact.
Risk avoidance is appropriate when a risk cannot otherwise be reduced, but it is not justified here because mitigation options exist and building the component internally may introduce new risks, timelines, and costs.
Risk acceptance is appropriate for low-probability or low-impact risks; a high failure rate on a required critical component represents a significant threat that warrants an active response rather than passive acceptance.
Risk mitigation involves taking proactive steps to reduce the probability or impact of a risk event before it occurs. Requiring quality checkpoints on the external partner's work targets the root cause - high failure rate - by catching defects early in the production process, reducing the likelihood that a failed component reaches the launch stage and jeopardizes the project.
Concept tested: Risk response strategy selection - mitigation vs alternatives
Source: https://www.pmi.org/learning/library/risk-management-strategies-7070
Topics
Community Discussion
No community discussion yet for this question.