A project manager realizes there is a lot of variability in the estimates received for task duration, primarily because more than one estimating source was used. While sequencing the tasks, the…
The correct answer is C. Program Evaluation Review Technique (PERT). The Program Evaluation Review Technique, or PERT, is a visual tool used in project planning.
Tools and documentation
Question
A project manager realizes there is a lot of variability in the estimates received for task duration, primarily because more than one estimating source was used. While sequencing the tasks, the project manager wants to ensure the variability is accounted for within the network diagram. Which of the following network diagramming methods/techniques should the project manager use?
Options
- AArrow diagramming method
- BWork breakdown structure
- CProgram Evaluation Review Technique (PERT)
- DScheduling performance index
How the community answered
(30 responses)- A3% (1)
- B10% (3)
- C80% (24)
- D7% (2)
Explanation
The Program Evaluation Review Technique, or PERT, is a visual tool used in project planning.
Topics
#PERT#network diagram#schedule estimation#duration variability