Question
A new project manager is taking over a project that is already in the execution phase, and is conducting a review of all meetings to identify usefulness and content. Team members have complained of an overabundance of meetings. Which of the following would be useful to identify who should be required to attend?
Options
- ACompare participation to the list of attendees in the meeting minutes.
- BReview the communication plan.
- CReview the meeting minutes for appropriate subject material
- DCompare scheduled duration to actual duration.