PK0-004 · Question #822

PK0-004 Question #822: Real Exam Question with Answer & Explanation

The correct answer is A: An issue occurs.. An issue is def something you want to update the risk register.

Question

Which of the following is the MOST likely trigger to update the project risk register?

Options

  • AAn issue occurs.
  • BA quality audit is passed.
  • CA project milestone is completed.
  • DA stakeholder initiates a change request.

Explanation

An issue is def something you want to update the risk register.