The correct answer is A: An issue occurs.. An issue is def something you want to update the risk register.
Question
Which of the following is the MOST likely trigger to update the project risk register?
Options
- AAn issue occurs.
- BA quality audit is passed.
- CA project milestone is completed.
- DA stakeholder initiates a change request.
Explanation
An issue is def something you want to update the risk register.