PK0-004 · Question #813
A project manager has developed a schedule in which all tasks start as late as possible, and there is a focus on buffer utilization and work being completed in shorter periods of time. Which of the…
The correct answer is A. Critical chain. Critical chain project management (CCPM) is a method of planning and managing projects that emphasizes the resources (people, equipment, physical space) required to execute project tasks.
Question
A project manager has developed a schedule in which all tasks start as late as possible, and there is a focus on buffer utilization and work being completed in shorter periods of time. Which of the following methods is the project manager MOST likely using to develop the schedule?
Options
- ACritical chain
- BBaseline
- CPrecedence diagram
- DArrow diagram
- ESprint plan
How the community answered
(41 responses)- A73% (30)
- B7% (3)
- C2% (1)
- D15% (6)
- E2% (1)
Explanation
Critical chain project management (CCPM) is a method of planning and managing projects that emphasizes the resources (people, equipment, physical space) required to execute project tasks.