nerdexam
CompTIA

PK0-004 · Question #813

A project manager has developed a schedule in which all tasks start as late as possible, and there is a focus on buffer utilization and work being completed in shorter periods of time. Which of the…

The correct answer is A. Critical chain. Critical chain project management (CCPM) is a method of planning and managing projects that emphasizes the resources (people, equipment, physical space) required to execute project tasks.

Tools and documentation

Question

A project manager has developed a schedule in which all tasks start as late as possible, and there is a focus on buffer utilization and work being completed in shorter periods of time. Which of the following methods is the project manager MOST likely using to develop the schedule?

Options

  • ACritical chain
  • BBaseline
  • CPrecedence diagram
  • DArrow diagram
  • ESprint plan

How the community answered

(41 responses)
  • A
    73% (30)
  • B
    7% (3)
  • C
    2% (1)
  • D
    15% (6)
  • E
    2% (1)

Explanation

Critical chain project management (CCPM) is a method of planning and managing projects that emphasizes the resources (people, equipment, physical space) required to execute project tasks.

Topics

#critical chain#schedule development#buffer management#scheduling methods

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice