Because a feature was not meeting documented requirements, a project milestone was not achieved as scheduled. Which of the following activities should the project manager perform NEXT?

The correct answer is D. Schedule a meeting with stakeholders and update the project objectives. Meeting and taking the stakeholders in confidence is much more important than any step in the project completion process.

Project life cycle phases

Question

Because a feature was not meeting documented requirements, a project milestone was not achieved as scheduled. Which of the following activities should the project manager perform NEXT?

Options

  • ACalculate the schedule variance and update the project status.
  • BUpdate the project scope and obtain sponsor approval.
  • CReview quality control processes and make the necessary improvements.
  • DSchedule a meeting with stakeholders and update the project objectives.

How the community answered

(47 responses)
  • A
    9% (4)
  • B
    17% (8)
  • C
    4% (2)
  • D
    70% (33)

Explanation

Meeting and taking the stakeholders in confidence is much more important than any step in the project completion process.

Topics

#milestone management#requirements#stakeholder communication#project objectives