A project manager has laid out a network diagram and is beginning to schedule activities for an upcoming project. Which of the following activities should be performed LAST?

The correct answer is B. Determine the critical path. Building a project schedule from a network diagram requires identifying dependencies and durations before dates can be set, and the critical path can only be calculated after all prior steps are complete.

Tools and documentation

Question

A project manager has laid out a network diagram and is beginning to schedule activities for an upcoming project. Which of the following activities should be performed LAST?

Options

  • ADetermine the start/finish dates.
  • BDetermine the critical path.
  • CDetermine the dependencies.
  • DDetermine the task durations.

How the community answered

(54 responses)
  • A
    11% (6)
  • B
    81% (44)
  • C
    2% (1)
  • D
    6% (3)

Why each option

Building a project schedule from a network diagram requires identifying dependencies and durations before dates can be set, and the critical path can only be calculated after all prior steps are complete.

ADetermine the start/finish dates.

Start and finish dates are calculated after dependencies and durations are established, so they come before the critical path is determined, not last.

BDetermine the critical path.Correct

Determining the critical path is the final scheduling step because it requires knowing all activity dependencies, individual task durations, and calculated start and finish dates first. Only once the full network is populated with durations and dates can the longest path through the project be identified.

CDetermine the dependencies.

Dependencies must be identified first to build the network diagram structure; they are the earliest step in the scheduling sequence.

DDetermine the task durations.

Task durations are estimated after dependencies are known but before dates or the critical path can be calculated.

Concept tested: Network diagram scheduling sequence and critical path determination

Source: https://www.pmi.org/learning/library/schedule-network-analysis-critical-path-6154

Topics

#network diagram#critical path method#scheduling#task dependencies