nerdexam
ExamsPK0-004Questions#750
CompTIA

PK0-004 · Question #750

PK0-004 Question #750: Real Exam Question with Answer & Explanation

The correct answer is B: Determine the critical path.. Building a project schedule from a network diagram requires identifying dependencies and durations before dates can be set, and the critical path can only be calculated after all prior steps are complete.

Question

A project manager has laid out a network diagram and is beginning to schedule activities for an upcoming project. Which of the following activities should be performed LAST?

Options

  • ADetermine the start/finish dates.
  • BDetermine the critical path.
  • CDetermine the dependencies.
  • DDetermine the task durations.

Explanation

Building a project schedule from a network diagram requires identifying dependencies and durations before dates can be set, and the critical path can only be calculated after all prior steps are complete.

Common mistakes.

  • A. Start and finish dates are calculated after dependencies and durations are established, so they come before the critical path is determined, not last.
  • C. Dependencies must be identified first to build the network diagram structure; they are the earliest step in the scheduling sequence.
  • D. Task durations are estimated after dependencies are known but before dates or the critical path can be calculated.

Concept tested. Network diagram scheduling sequence and critical path determination

Reference. https://www.pmi.org/learning/library/schedule-network-analysis-critical-path-6154

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice