PK0-004 · Question #723

Which of the following is the BEST technique for comparing actual or planned project practices to those of comparable projects?

The correct answer is A. Benchmarking. Benchmarking is the process of comparing your project's practices, processes, or performance metrics against those of similar projects or industry standards to identify best practices and areas for improvement. It is explicitly a comparative tool. A Pareto chart identifies the…

Tools and documentation

Question

Which of the following is the BEST technique for comparing actual or planned project practices to those of comparable projects?

Exhibit

PK0-004 question #723 exhibit

Options

  • ABenchmarking
  • BPareto chart
  • CHistogram
  • DFishbone diagram

How the community answered

(18 responses)
  • A
    94% (17)
  • C
    6% (1)

Explanation

Benchmarking is the process of comparing your project's practices, processes, or performance metrics against those of similar projects or industry standards to identify best practices and areas for improvement. It is explicitly a comparative tool. A Pareto chart identifies the most significant causes of defects (80/20 rule). A histogram shows frequency distribution of data. A fishbone (Ishikawa) diagram identifies root causes of a problem. None of these involve comparison to external or comparable projects.

Topics

#benchmarking#quality management#best practices comparison#process improvement