A project manager is taking over an international project that is in progress and realizes redundant work is being performed by teams in different countries. Which of the following documents would…

The correct answer is D. Project communication plan. The lack of communication and status updates are causing the issue of the same work getting performed by teams in different countries.

Tools and documentation

Question

A project manager is taking over an international project that is in progress and realizes redundant work is being performed by teams in different countries. Which of the following documents would help resolve this issue?

Options

  • AProject scope statement
  • BProject charter
  • CStatus report
  • DProject communication plan

How the community answered

(51 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    4% (2)
  • D
    92% (47)

Explanation

The lack of communication and status updates are causing the issue of the same work getting performed by teams in different countries.

Topics

#project communication plan#redundancy resolution#international teams#stakeholder coordination