PK0-004 · Question #719
Which of the following is the BEST reason to use a burndown chart?
The correct answer is C. To establish a backlog for project deliverables. A burndown chart is a tool used by Agile teams to gather information about work completed on a project and work to be done in a given time period. Often, teams can use their burndown chart as a prediction tool that allows them to visualize when their project will be completed.
Question
Which of the following is the BEST reason to use a burndown chart?
Options
- ATo determine how much risk is still associated with the project
- BTo present the risks in criticality rating
- CTo establish a backlog for project deliverables
- DTo create a project charter
How the community answered
(62 responses)- A2% (1)
- B3% (2)
- C92% (57)
- D3% (2)
Explanation
A burndown chart is a tool used by Agile teams to gather information about work completed on a project and work to be done in a given time period. Often, teams can use their burndown chart as a prediction tool that allows them to visualize when their project will be completed.