A project team is currently three weeks behind in a project with six more weeks to go. Although the project manager believes the project can be fast tracked to save a week, this is not the case…

The correct answer is C. 0 weeks. Float or slack is always zero on the critical path

Tools and documentation

Question

A project team is currently three weeks behind in a project with six more weeks to go. Although the project manager believes the project can be fast tracked to save a week, this is not the case. Which of the following represents the slack along the critical path?

Options

  • A-3 weeks
  • B-2 weeks
  • C0 weeks
  • D2 weeks
  • E3 weeks

How the community answered

(57 responses)
  • A
    7% (4)
  • B
    2% (1)
  • C
    74% (42)
  • D
    14% (8)
  • E
    4% (2)

Explanation

Float or slack is always zero on the critical path

Topics

#critical path#float and slack#schedule compression#fast tracking