CompTIA
PK0-004 · Question #713
A project team is currently three weeks behind in a project with six more weeks to go. Although the project manager believes the project can be fast tracked to save a week, this is not the case…
The correct answer is C. 0 weeks. Float or slack is always zero on the critical path
Tools and documentation
Question
A project team is currently three weeks behind in a project with six more weeks to go. Although the project manager believes the project can be fast tracked to save a week, this is not the case. Which of the following represents the slack along the critical path?
Options
- A-3 weeks
- B-2 weeks
- C0 weeks
- D2 weeks
- E3 weeks
How the community answered
(57 responses)- A7% (4)
- B2% (1)
- C74% (42)
- D14% (8)
- E4% (2)
Explanation
Float or slack is always zero on the critical path