Question

A project team is currently three weeks behind in a project with six more weeks to go. Although the project manager believes the project can be fast tracked to save a week, this is not the case. Which of the following represents the slack along the critical path?

Options

  • A-3 weeks
  • B-2 weeks
  • C0 weeks
  • D2 weeks
  • E3 weeks