PK0-004 · Question #710

In a projectized organization, which of the following occurs FIRST at the completion of a project?

The correct answer is B. Resources are assigned to new projects. One of the biggest drawbacks of a projectized organization is reassigning project team members once the project ends. There may not always be a new project waiting for these resources.

Project management concepts

Question

In a projectized organization, which of the following occurs FIRST at the completion of a project?

Options

  • AResources are allocated to the PMO.
  • BResources are assigned to new projects
  • CResources are transferred to operations.
  • DResources are released to functional managers.

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    92% (22)
  • D
    4% (1)

Explanation

One of the biggest drawbacks of a projectized organization is reassigning project team members once the project ends. There may not always be a new project waiting for these resources.

Topics

#projectized organization#resource release#project closure#organizational structure