In a projectized organization, which of the following occurs FIRST at the completion of a project?
The correct answer is B. Resources are assigned to new projects. One of the biggest drawbacks of a projectized organization is reassigning project team members once the project ends. There may not always be a new project waiting for these resources.
Project management concepts
Question
In a projectized organization, which of the following occurs FIRST at the completion of a project?
Options
- AResources are allocated to the PMO.
- BResources are assigned to new projects
- CResources are transferred to operations.
- DResources are released to functional managers.
How the community answered
(24 responses)- A4% (1)
- B92% (22)
- D4% (1)
Explanation
One of the biggest drawbacks of a projectized organization is reassigning project team members once the project ends. There may not always be a new project waiting for these resources.
Topics
#projectized organization#resource release#project closure#organizational structure