Question
A key stakeholder has asked project team members to work overtime on special projects. This is undermining the success of a time-sensitive project because the project team is too tired to complete the deliverables. Which of the following steps should the project manager take to BEST resolve the issue?
Options
- AAsk the project sponsor for shared resources for the key stakeholder's project.
- BAsk the project sponsor for benched resources for the time-sensitive project.
- CAsk the key stakeholder for low-quality resources for the time-sensitive project.
- DAsk the project sponsor for dedicated resources for the time-sensitive project.