PK0-004 · Question #683
During a routine risk review, the project champion analyzes the status of multiple projects. A potential risk is discovered that will delay project A due to the interdependencies with project B. The…
The correct answer is D. Qualification. After identifying the risks and triggers, perform a qualitative analysis.
Project management concepts
Question
During a routine risk review, the project champion analyzes the status of multiple projects. A potential risk is discovered that will delay project A due to the interdependencies with project B. The project champion schedules a meeting with the project managers. Which of the following risk activities is MOST likely happening?
Options
- AIdentification
- BRegistration
- CQuantification
- DQualification
How the community answered
(31 responses)- A3% (1)
- B3% (1)
- C10% (3)
- D84% (26)
Explanation
After identifying the risks and triggers, perform a qualitative analysis.
Topics
#risk qualification#risk review#project interdependencies#risk activities