PK0-004 · Question #683

During a routine risk review, the project champion analyzes the status of multiple projects. A potential risk is discovered that will delay project A due to the interdependencies with project B. The…

The correct answer is D. Qualification. After identifying the risks and triggers, perform a qualitative analysis.

Project management concepts

Question

During a routine risk review, the project champion analyzes the status of multiple projects. A potential risk is discovered that will delay project A due to the interdependencies with project B. The project champion schedules a meeting with the project managers. Which of the following risk activities is MOST likely happening?

Options

  • AIdentification
  • BRegistration
  • CQuantification
  • DQualification

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    10% (3)
  • D
    84% (26)

Explanation

After identifying the risks and triggers, perform a qualitative analysis.

Topics

#risk qualification#risk review#project interdependencies#risk activities