A project manager for a projectized organization is notified that a team member is ill and will be out for an extend period of time. This team member is the only person with a key skill set. Which…
The correct answer is D. Project team. The PM should notify the project team since the tasks will need to be redelegated and the use the risk response plan.
Project management concepts
Question
A project manager for a projectized organization is notified that a team member is ill and will be out for an extend period of time. This team member is the only person with a key skill set. Which of the following should the project manager notify FIRST regarding the team member’s absence?
Options
- AProject sponsor
- BHuman resources office
- CBudget office
- DProject team
How the community answered
(27 responses)- A4% (1)
- B7% (2)
- C19% (5)
- D70% (19)
Explanation
The PM should notify the project team since the tasks will need to be redelegated and the use the risk response plan.
Topics
#resource management#team communication#stakeholder notification#projectized organization