PK0-004 · Question #65

Which of the following techniques modifies the schedule based upon resource constraints?

The correct answer is A. Critical Chain Method. The critical chain method is a schedule network analysis method that allows you to consider resource limitations and adjust the schedule as appropriate to work within those limitations. The critical chain is established by analyzing the critical path alongside the resources…

Tools and documentation

Question

Which of the following techniques modifies the schedule based upon resource constraints?

Options

  • ACritical Chain Method
  • BCritical Path Method
  • CArrow Diagramming Method
  • DPrecedence Diagramming Method

How the community answered

(52 responses)
  • A
    88% (46)
  • B
    2% (1)
  • C
    8% (4)
  • D
    2% (1)

Explanation

The critical chain method is a schedule network analysis method that allows you to consider resource limitations and adjust the schedule as appropriate to work within those limitations. The critical chain is established by analyzing the critical path alongside the resources that are actually available. The critical chain method is also used to plan and manage reserves or buffers and helps mitigate possible cost and schedule risks.

Topics

#critical chain method#resource constraints#scheduling techniques#schedule compression