nerdexam
CompTIA

PK0-004 · Question #648

A company is about to initiate a cybersecurity project. However, the project manager realizes the company does not possess the required skills to complete the project and requires a search by…

The correct answer is A. RFI. An RFI is used when you need to gather more information about the goods or services you need to procure. This process will give you a sense for the number of providers or contractors who can provide the goods or services, and you will get an idea of cost. An RFI or RFQ is used…

Tools and documentation

Question

A company is about to initiate a cybersecurity project. However, the project manager realizes the company does not possess the required skills to complete the project and requires a search by third-party vendors. Which of the following documents should the project manager provide?

Options

  • ARFI
  • BLOI
  • CRFP
  • DRFQ

How the community answered

(45 responses)
  • A
    96% (43)
  • B
    2% (1)
  • D
    2% (1)

Explanation

An RFI is used when you need to gather more information about the goods or services you need to procure. This process will give you a sense for the number of providers or contractors who can provide the goods or services, and you will get an idea of cost. An RFI or RFQ is used when the costs are unknown to you and you need an estimate for the goods or services.

Topics

#procurement management#RFI#vendor selection#procurement documents

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice