A project is approaching its end when the project manager is informed that a deliverable is exceeding the upper noise limit set by the legislation of the country where it was implemented. Which of…

The correct answer is C. Environment. Environment is not a constraint of project manager scope and quality are.

Project management concepts

Question

A project is approaching its end when the project manager is informed that a deliverable is exceeding the upper noise limit set by the legislation of the country where it was implemented. Which of the following constraints has MOST likely been overlooked?

Options

  • AScope
  • BResources
  • CEnvironment
  • DQuality

How the community answered

(60 responses)
  • A
    12% (7)
  • B
    3% (2)
  • C
    77% (46)
  • D
    8% (5)

Explanation

Environment is not a constraint of project manager scope and quality are.