Which of the following risk management activities identifies the severity of a risk event?
The correct answer is A. Quantification. The risk has already been identified. Qualitative Analysis will check the magnitude of the risk on
Project management concepts
Question
Which of the following risk management activities identifies the severity of a risk event?
Options
- AQuantification
- BIdentification
- CResponse
- DMitigation
How the community answered
(27 responses)- A93% (25)
- B4% (1)
- C4% (1)
Explanation
The risk has already been identified. Qualitative Analysis will check the magnitude of the risk on
Topics
#risk management#risk quantification#severity assessment