PK0-004 · Question #620
A project is nearing the expected completion date, but it is behind schedule. The project manager has decided to fast-track the resources. Which of the following impacts will MOST likely occur?…
The correct answer is A. Cost will increase. E. Budget will increase. Fast-tracking is a technique where activities that would have been performed sequentially using the original schedule are performed in parallel. fast tracking can only be applied if the activities in question can actually be overlapped. When you need to compress a schedule, you…
Question
A project is nearing the expected completion date, but it is behind schedule. The project manager has decided to fast-track the resources. Which of the following impacts will MOST likely occur? (Choose two.)
Options
- ACost will increase.
- BScope will increase.
- CSchedule will decrease.
- DRisk will decrease.
- EBudget will increase.
- FQuality will increase.
How the community answered
(48 responses)- A71% (34)
- B4% (2)
- C2% (1)
- D8% (4)
- F15% (7)
Explanation
Fast-tracking is a technique where activities that would have been performed sequentially using the original schedule are performed in parallel. fast tracking can only be applied if the activities in question can actually be overlapped. When you need to compress a schedule, you should consider this technique first, because fast tracking usually does not involve any costs. fast tracking may not result in an increase in the cost, it leads to an increase in the risk, because activities now being performed in parallel may lead to needing to rework or rearrange the project.
Topics