The correct answer is D: Communication. No communication about the mitigation plan. That's why the issue kept being raised.
Question
At each project team meeting, the project team raises the same risk repeatedly. A mitigation plan has been developed since the risk was initially identified. Which of the following risk activities is MOST likely missing since the identification?
Options
- AQuantification
- BResponse
- CPrioritization
- DCommunication
- EReview
Explanation
No communication about the mitigation plan. That's why the issue kept being raised.