The correct answer is D: Communication. No communication about the mitigation plan. That's why the issue kept being raised.

Question

At each project team meeting, the project team raises the same risk repeatedly. A mitigation plan has been developed since the risk was initially identified. Which of the following risk activities is MOST likely missing since the identification?

Options

  • AQuantification
  • BResponse
  • CPrioritization
  • DCommunication
  • EReview

Explanation

No communication about the mitigation plan. That's why the issue kept being raised.