PK0-004 · Question #619
At each project team meeting, the project team raises the same risk repeatedly. A mitigation plan has been developed since the risk was initially identified. Which of the following risk activities…
The correct answer is D. Communication. No communication about the mitigation plan. That's why the issue kept being raised.
Project management concepts
Question
At each project team meeting, the project team raises the same risk repeatedly. A mitigation plan has been developed since the risk was initially identified. Which of the following risk activities is MOST likely missing since the identification?
Options
- AQuantification
- BResponse
- CPrioritization
- DCommunication
- EReview
How the community answered
(21 responses)- A5% (1)
- B14% (3)
- D76% (16)
- E5% (1)
Explanation
No communication about the mitigation plan. That's why the issue kept being raised.
Topics
#risk communication#risk management process#risk monitoring#risk review