PK0-004 · Question #615
A project is moving into the next phase, and those involved with planning will not actually perform the work. After the project team members have been identified and assigned to do the work, which…
The correct answer is D. Stakeholder. When the actual doers of the work are identified and assigned, the stakeholder group changes. Previously, stakeholders consisted of the planning team and others involved in scoping the project. Once execution-phase team members are formally assigned, new individuals with a…
Question
A project is moving into the next phase, and those involved with planning will not actually perform the work. After the project team members have been identified and assigned to do the work, which of the following has changed?
Options
- AProject
- BSchedule
- CBaseline
- DStakeholder
How the community answered
(46 responses)- A7% (3)
- B11% (5)
- C2% (1)
- D80% (37)
Explanation
When the actual doers of the work are identified and assigned, the stakeholder group changes. Previously, stakeholders consisted of the planning team and others involved in scoping the project. Once execution-phase team members are formally assigned, new individuals with a direct stake in the project outcome are added to the stakeholder register. The project itself (A) has not changed, the schedule (B) may be influenced but is not what fundamentally changed, and the baseline (C) remains the original approved plan. The stakeholder composition is what shifts when new personnel are brought on board.
Topics
Community Discussion
No community discussion yet for this question.